Work continues across Overseas West Sector A, and this field report records where each street stands, from finished paving to early earthmoving.
### Street Number 1
Along Street Number 1, the road corridor has been earthworked and filled with soil. Watering and ground preparation are complete, leaving the surface ready for tuff tiles. Utility poles stand on one side, but the street light fixtures still need fitting. The other side has yet to see footpath work, with extra poles and fixtures planned for later phases.
### Street Number 2
Street Number 2 shows heavier paving progress. Roughly 80 percent of the tuff tiles were laid across the developed segment. On the unfinished patch, material has arrived, earth has been spread, and watering plus compaction must finish before tiles go down. Completed stretches carry both poles and working street lights, and walkways on both sides are largely paved. Even so, the street is not finished end to end: only around half of the corridor, up to specific mapped plots, has been paved, and the stretch beyond shows no active work.
### Lane Number 16
Lane Number 16 sits behind the plots facing the Ring Road inside Sector A. Sand and sub-base are down, with watering and compaction close to finished. Footpath paving is in progress, and on-site teams handle tile delivery and fixing. Past Street Number 3 along Lane 16, the road surface is tiled across most of the section, leaving only minor edge detailing and final finishing.
### Street Number 3
Street Number 3 is well advanced. Nearly 90 percent of the road surface now carries tuff tiles. Crews are closing a small remaining strip so it joins cleanly with the neighboring paths, placing pavers by hand on the compacted base, which leaves this section near structural completion.
### Street Number 4 and Street Number 5
On Street Number 4, the footpath frame is almost finished on both sides, with small gaps left for final tiling and pavers stacked nearby. The developed road surface is tiled on both sides. Still, only about 40 to 45 percent of the full alignment is built, so plots farther along have no road works yet, and street lighting poles have not been placed.
Street Number 5 follows much the same pattern. The developed main road is paved, and its tie-in with Lane Number 16 needs only final edge alignment. Part of the pedestrian footpath still requires finishing, light poles are yet to be erected, and work covers roughly 40 to 45 percent of the mapped length, with no construction visible on the remaining section.
### Street Number 6 and Street Number 7
Deeper into Sector A, the focus shifts from surfacing to foundation earthworks. Street Number 6 has had initial ground leveling, and concrete kerb stones mark the footpath boundaries on both sides, fixing the structural corridor. Tuff tile installation for the carriageway and walkways has not begun, and will wait until surfacing machinery and paving teams advance from earlier streets.
On Street Number 7, heavy earthmoving equipment has completed basic ground leveling. Kerbs are aligned along one side to outline the walkway, while the opposing side awaits curbing. Underground sewerage remains partially incomplete along this corridor, so full-scale surface development and tile paving will follow the completion of foundational utilities.
### Street Number 8 and Street Number 9
Street Number 8 runs alongside an adjacent designated neighborhood park area. Basic leveling across the road alignment is complete, and curb stones define the perimeter of the green space; footpath completion and road paving remain pending. Street Number 9 reflects the same stage: the surface has been leveled, a curved curb line borders the open park quadrant, but roadway surfacing, opposite-side footpaths, and electrical pole installations are yet to take place.
### Street Number 10, Street Number 11, and Beyond
Street Number 10 centers on deep utility infrastructure. Approximately 80 to 90 percent of the underground sewerage network has been installed, though road leveling, curbing, and surfacing works remain on hold pending final utility sign-off.
Street Number 11 currently consists of raw earth mounds and initial excavation areas where digging commenced previously. No resurfacing, leveling, or structural paving activity has advanced here recently. Looking past Street Number 11 toward the outer perimeter plots and areas facing the Ring Road adjacent to the executive sector, the ground remains raw and undeveloped, unchanged compared to previous survey periods.